Optimized integration of renewable energy into morocan power system

Intégration optimisée des Energies Renouve-lables dans le système électrique marocain

Project details

  • Project number:2017.2039.0
  • Status:Projekt beendet
  • Responsible Organisational unit: 3600 Nordafrika
  • Contact address: Transparency team 
  • Partner countries: Morocco

Summary

  • Objectives:

    The capacities of Moroccan state actors in the energy sector to integrate electricity generation from variable renewable energies are strengthened.

  • Client:

    Bundesministerium für wirtschaftliche Zusammenarbeit u. Entwicklung

  • Project partner:

    Energieministerium Marokko

  • Financing organisation:

    not available

 

Volume of commission

  • Financial commitment for the actual implementation phase:5 000 000 Euro

Cofinancing

  • not available

 

Previous project

  • not available

Follow-on project

  • not available

 

Term

  • Entire project:
    (including all previous, current and following project implementation phases, if existing)
    26.08.2019 - 30.01.2025
  • Actual project implementation phase:01.01.2020 - 30.01.2025

other participants

  • Moeller & Poeller Engineering

 

Further information

  • Project websitesnot available

 

Policy markers

  • Climate Change: Mitigation

    Principal (primary) policy objective

CRS code

    23630 Electric power transmission and distribution (centralised grids)

Evaluation