Support of the water sector reform

Project details

  • Project number:2008.2094.4
  • Status:Projekt beendet
  • Responsible Organisational unit: 1100 Westafrika 1 und Zentralafrika
  • Contact address: Transparency team 
  • Partner countries: Dem. Rep. Congo

Summary

  • Objectives:

    Water sector reform has been implemented and the Congolese authorities and downstream agencies are carrying out the ensuing tasks.

  • Client:

    BMZ

  • Project partner:

    Ministère de l'Energie et Ressources Hydrauliques

  • Financing organisation:

    not available

 

Volume of commission

  • Financial commitment for the actual implementation phase:4 000 000 Euro

Cofinancing

  • not available

 

Previous project

  • 2007.2064.9

    KV - Unterstützung der Wassersektorreform

Follow-on project

  • 2010.2041.1

    Sektorprogramm Wasser/Abwasser (PROSECO)

 

Term

  • Entire project:
    (including all previous, current and following project implementation phases, if existing)
    23.09.2005 - 30.01.2022
  • Actual project implementation phase:19.06.2009 - 25.04.2013

other participants

  • not available

 

Further information

  • Project websitesnot available

 

Policy markers

  • Gender Equality

    Significant (secondary) policy objective

  • Climate Change: Adaptation

    Significant (secondary) policy objective

CRS code

    14010 Water sector policy and administrative management

Evaluation

not available